Magellan Marine International L.L.C. 2816 Athania Parkway Metairie, Louisiana 70002 (504) 835-3009 (504) 835-7040 Fax |
||
|
|
Technical Personnel |
|
| Supplemental Paperwork | ||
|
Pipe and Crossing Report: This report will be filled out for all pipeline crossings and hot taps. Only one crossing per sheet, even if the crossed line are adjacent. This is a very important report and time needs to be taken to insure completion and accuracy. This report is also used for land jobs, so not all blanks will apply. Type in all CAPS, it helps to read the faxes.
Foreman No.: Your name plus the MMI job number. If there is more than one drawing use a hyphen and number sequentially, such as 970711-1.
Area No.: Put the area (no initials) and block number: South Timbalier 211 Date of Occurrence: Date crossing or hot tap made.
City: Offshore, GOM (Gulf of Mexico)
County: NA
State: Federal (or State) Waters
System Check One: Put in the pipeline system; ask MMI if you don't know.
Facility Name/Description: Again, put in the pipeline system
Map/Drawing No.:
Survey Station:
Air/Mile Marker: NA
Nominal Dia., W.T. or U.T., Grade, Type:
Corrosion & Coating Information (info on Existing Pipeline): Check all appropriate boxes or state NA if it doesn't apply. For "Coating Type" put CONCRT (concrete) or FBE (fusion bond epoxy) or other correct term. This is for the existing Shell pipeline.
Foreign Structure: This is the crossing pipeline; correctly fill in all you can. In Type/Utility check other and add either Oil or Gas next to it. Structure Material can be Steel Line Pipe. List the major contractor and secondary if required, like McDermott/Cal-Dive. Add main contact phone number for contractor rep. Piping Change: Fill in for Hot Taps. Include new pipe info here.
Sketch/Description:
Very Important! Must have a detailed verbal picture. Repeat the Block Number and
the X-Y coordinates. Add water depth, top of pipes, burial, suspension lengths,
number of mats or bags, separation, angle of crossing (Show "North"
direction), bottom conditions, Survey Unit of Measurement (for surveyor). Also,
use Excel's drawing tools to make a small but correct drawing as shown in the
example. An additional, a more complete (as in Designer)
Damage: Check appropriate box, and boy, I hope nothing was damaged.
Signature----Title----Telephone----Date Completed: Enter the corresponding information.
Change to Piping Report Example
This report is also used for hot taps, repairs, and any other changes to our client pipelines.
Anchor and Pipeline Crossing Report Example
Anchor Positioning Log Example
Include two copies with your report and make sure MMI gets a complete job copy on disk. With any questions, call Mike or John.
|
||